RFQ - Buckley SFB Rectifier Inverter System Replacement

Deadline
Closed (was August 21, 2026)
Jurisdiction
Federal
Sectors
ev-charging

What the buyer wants

RFI – Clarification Questions 12 August 2026 1. While the SOW references power down windows, please confirm whether any hot cutovers will be required as part of this effort. All work related to the transition from the old system over to the new system will have to be completed without interrupting equipment located in room 132. The only exception is the cutover from the inverter A/C circuits, but